Completing Corrective Actions

ℹ️ NOTE: Health & Safety Report Corrective Actions are categorized under the task headers as either HS-Injury or HS-Near Miss.  This is dependent on which health & safety report category is chosen.

To complete Health & Safety Corrective Actions:

  1. Go to Logistics > Tasks 
  2. Locate the applicable Corrective Action task, they will be listed under the heading HS-Category (I.e. Injury  / Near Miss)
  3. Click on the task you wish to complete
  4. Update the Status of the Corrective Action task to either In Progress or Completed
  5. Once you have completed all corrective action tasks you will see this update on the Health & Safety screen
  6. A green check mark will appear under the Corrective Actions header

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us